Project

Buildings Required fire flow is looked up from Table B105.2 by fire-flow calculation area and construction type.

# Phase Bldg # Building Name Stories Anticipated SF Expected Occupancy Architect Remarks Construction IBC Fire Flow Group Spk? NFPA Std Flow Rate (gpm) Duration (hr) Adj. Flow (gpm) Adj. Duration (hr)
Anticipated SF = fire-flow calculation area (IFC B104). Cells in blue show base flow; orange shows sprinkler-reduced flow.

Site Summary

Governing Site Fire Flow
gpm
Max Required Duration
hr
Buildings
0
Total Anticipated SF
0ft²

Method

This tool implements IFC 2021 Appendix B Table B105.2 — required fire flow and duration for buildings other than one- and two-family dwellings, Group R-3 and R-4 buildings, and townhouses.

Lookup by construction group

Each row of Table B105.2 specifies a maximum fire-flow calculation area for each of five construction groups, mapped from IBC types per NFPA 220:

Sprinkler reduction

When the building is sprinklered, the required fire flow is reduced to max(0.25 × required, floor) where the floor is 1,000 gpm for NFPA 13 systems and 1,500 gpm for NFPA 13R systems. The adjusted duration is then mapped from the adjusted flow rate:

Floors used here are conservative and match the source spreadsheet. IFC 2021 B105.2 itself permits a 75% reduction with NFPA 13 to a minimum of 600 gpm. Confirm AHJ-accepted criteria before use.

Scope / exclusions

This tool does not apply to one- and two-family dwellings, Group R-3 and R-4 buildings, or townhouses (see IFC B105.1). For those occupancies the base requirement is generally 1,000 gpm for 1 hour (areas ≤ 3,600 sq ft), with reduction to 500 gpm permitted for NFPA 13D sprinklered buildings.

Engineering aid only. Fire-flow calculation area, construction type, and sprinkler standard must be verified by the responsible engineer. The required fire flow is also subject to AHJ acceptance, water supply availability, and any locally adopted amendments to the IFC. This tool does not replace independent code analysis.